| CSFs
|
Projects
|
| 1,2,4 |
P1. |
Identify and analyze
causes of network failures.
- Identify sources of information, i.e. Help Desk log, Art’s
log, Building switches, etc.
- Examine for patterns
- Target weak elements
- Report on findings
- Develop proposal for addressing problems [include cost/benefit
analysis, ROI]
- Submit to management for action decision
- Review quarterly
|
| 1,2 |
P2. |
Develop a global picture
of inventory universe/procedures for using the available inventories.
|
| 4 |
P3. |
Implement internal
BGP Routing protocol. |
| 2 |
P4. |
Add additional
network monitoring and reporting. |
| 1,5 |
P5. |
Develop 5
and 20 year network (infrastructure) plans with annual review.
| 5 year Components |
|
20 year Components |
| Preferred components |
|
Infrastructure |
| New Construction & Infrastructure |
|
Conduit |
| Renovations Infrastructure |
|
Inclusion in Master Plan |
| Rebuild existing out-of-std networks |
|
Core Node Locations |
| |
|
NO specific equipment |
| |
|
Fiber Count? |
|
| 1,4 |
P6. |
Purchase, install, and
configure new, redundant routers and switches/Provide redundant
feed to each building.
- Inventory existing equipment and fiber optic wiring
- Perform internal design and cost analysis
- Submit to management
- Acquire approval and funding
- Purchase, install, and relocate equipment
|
| 1,2 |
P7. |
Identify
departmental technicians and their network tasks.
- Obtain contacts list.
- Begin to work with contacts on network installation and
related issues.
- Revisit after specified period for enhancements, etc.
|
| 1
|
P8. |
Develop preventative
maintenance program for communications closet UPS batteries.
- Inventory UPS’s in wiring closets (~400)
- Test each unit against criteria (Is criteria developed?
If not, Step 1.)
- Create log with pertinent info for current and future reference
- Purchase new batteries
- Install new batteries, log
- Review cycles of replacements for diagnostics/cost/ROI
|
| 2
|
P9. |
Implement
environmental monitoring and control for wiring closets. |
| 2
|
P10. |
Develop SNMP agent to
monitor network. |
| 1,4
|
P11. |
Implement “out-of-bounds”
management at critical nodes. |
| 3
|
P12. |
Upgrade
outdated switches and hubs with current standards-based equipment.
|
| 3
|
P13. |
Upgrade
outdated data wiring to current University standard.
- Identify wiring that
needs to be upgraded
- Inventory
- Engineering
- Itemize replacements
- Electrical Conduit (Campus Design)
- Initiate OTC process/request a set of as-builts
- Incorporate results into 5 year plan (see project #5)
|
| 2
|
P14. |
Install smart UPS in
all communications closets. |
| 1,3
|
P15. |
Install dedicated electrical
power outlets in all communications closets. |
| 1,2,5
|
P16. |
Station network
staff in zoned areas. |