1 6 February
2002
·
Introductions of team, project, methodology, ground rules.
·
Assignments
o
Rank the OTI Strategic Initiatives
o
Develop Critical Success Factors for each Initiatives
Workshop 1 20 February 2002
·
Review of Ground Rules
·
Review Initiative Ranking
·
CSF development for first two initiatives as ranked
o
Robust Networking
o
Privacy & Security
·
Assignments
o
Develop fully formed CSFs for remaining initiatives
o
Begin to formulate specific projects to accomplish success factors
Workshop
2 6 March 2002
·
Recap Ground Rules
·
Continue CSF development for remaining initiatives as ranked
o
Build World Class IT Infrastructure
o
Develop Self-Service Applications
o
Standardize Relational Database
o
Leverage Emerging Technologies
·
Assignments
o
Develop projects to accomplish each CSF
o
Brainstorm as a group to generate list of projects
o
Assign projects to individuals
o
Individual completes worksheet
o
Worksheets due to Team Liaison on 13 March 2002
o
List subject matter experts for projects
|
|
|||